Bharat Nirman Rajeev Gandhi Sewa Kendra |
State:RAJASTHAN | District:TONK | Block:UNIARA |
Work Code:2722002055/SK/5 | Work Name:Bharat Nirman Rajeev Gandhi Sewa Kendra,उनियारा |
Location: Panchayat -कुण्डेर Village -कुण्डेर Khata No.- Plot No.- |
Execution Level: Gram Panchayat | Executing Agency: Gram Panchayat |
Present Status: Not Existing | Proposed Status : New Construction |
Current Status: पूर्ण | Status Date : 15/12/2013 |
Sanction Detail |
Technical Sanction Detail |
Sanction No.: 616-2010 | Sanction Date : 24/02/2010 |
Sanction Amount Rs.(In lakhs): 10 | Labour Rs.(In lakhs): 0.89
Material (Skilled/Semiskilled + Material)Rs.(In lakhs) : (0+0 + 9.11) = 9.11
|
Area fixed by STATE Govt. (sq.feet): 1425 | Total Area to be Under taken for Construction (sq.feet): 1425 |
Wather construction work is being done within present premises? : | Y |
Whether construction work is being done according to MAP set by State Govt.? : | Y |
Financial Sanction Detail |
Sanction No.: 17436 | Sanction Date : 08/03/2010 |
Sanction Amount Rs.(In lakhs):10 |
Financial Sanction Amount detail (In Lakhs) |
Head | Amount(In Lakhs) |
---|
NREGA | 10 |
BRGF | 0 |
NABARD | 0 |
Expenditure Detail |
Muster Roll Filled | |
Muster Roll Expenditure (In Rs.) | 32203 |
Material Expenditure (In Rs.) | 586698.66813 |
Progress Detail |
Status Achived | Status Achived Date | Status Photo |
---|
|
Plinth Level | 11/10/2010 | |
|
Roof Level | 28/4/2011 | |
|
Roof Casted | 2/6/2011 | |
|
Finishing | 9/12/2011 | |
|
Completed | 13/1/2012 | |
BNRGSK