S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 1300 | 1300 |
2 | Site clearance, cutting grass, raking into heaps and removing off the premises | 0 | 0 | 0 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal) | 0.228 | 2862.14 | 652.56792 |
4 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Cement mortar 1:4 (1cement, 4sand) | 2.44 | 4109.75 | 10027.79 |
5 | Add for masonry in supper structure above plinth level up to floor two level | 2.2 | 252.64 | 555.808 |
6 | 15mm thick cement plaster on rough side of wall in-Cement mortar 1:4 (1cement, 4sand) | 11 | 159.25 | 1751.75 |
7 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work | 0.684 | 212.4 | 145.2816 |