S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 0 | 0 | 0 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 54.25 | 2894.9 | 157048.325 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 61 | 2228.1 | 135914.1 |
4 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 54.25 | 226.8 | 12303.9 |
5 | False work for R.C.C. and P.C.C. work in plinth and foundation | 71.2 | 126.6 | 9013.92 |
6 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Cement mortar 1:4 (1cement, 4sand) | 10.5 | 2324.4 | 24406.2 |
7 | 15mm thick cement plaster on rough side of wall in-Cement mortar 1:6 (1cement, 6sand) | 70 | 96.4 | 6748 |
8 | Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 30 Kms. and part there of upto 50 Kms. | 55.12 | 387.3 | 21347.976 |
9 | Transportation rates for Bricks, kanker, stone chips shingle & excavated materials in disintegrated rock & soft rock. | 10.5 | 681.3 | 7153.65 |
10 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 87.5 | 229.72 | 20100.5 |
11 | Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 50metres and upto 1.5metre.-Dence or hard soil | 560 | 9.3 | 5208 |
12 | Providing and fixing on Wall face Asbestos Cement building pipe of the following nominal size including jointing with sun yarn soaked in bitumen and cement mortar 1:2 (1cement, 2sand) complete .-100 mm dia. | 12 | 90.6 | 1087.2 |
13 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work | 42 | 54.4 | 2284.8 |
14 | Collection of hard moorum including stacking at quarry. | 87.5 | 118.36 | 10356.5 |
15 | Transportion of metal | 46.11 | 387.3 | 17858.403 |
16 | work charge | 1 | 20000 | 20000 |
17 | transportion of sand | 54.76 | 665.37 | 36435.6612 |
18 | TRANSPOTATION OF CEMENT | 62.44 | 198.27 | 12379.9788 |