S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Contingency | 1 | 23810 | 23810 |
2 | Labour only for item no.1279 | 1032 | 151.7 | 156554.4 |
3 | Collection of rubble masonry (size 0.014cum to 0.06cum) other then black trap, basalt or granite. | 154.8 | 475.3 | 73576.44 |
4 | Stacking and boxing.-Moorum or sand | 312.69 | 10.5 | 3283.245 |
5 | Stacking without boxing.-Masonry stones, pitching stones or boulders | 154.8 | 27.1 | 4195.08 |
6 | Transportation of metal | 154.8 | 531.16 | 82223.568 |
7 | Transportation of metal | 312.69 | 191.16 | 59773.8204 |
8 | Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing. | 247.68 | 41 | 10154.88 |
9 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work | 357.3 | 81.2 | 29012.76 |
10 | Collection of hard moorum including stacking at quarry. | 312.69 | 130.8 | 40899.852 |
11 | Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 20metres and upto 1.5metre.-Dense or hard soil. | 1290 | 12.8 | 16512 |