State: MADHYA PRADESH District: KHANDWA Block: PANDHANA Panchayat: LACHHORAKALA
Work Code: 1725007083/WC/22012034550756 (तालाब जल क्षमता विस्तारीकरन गंगु रुखदु के खेत पास)
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2020-2021 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : No Perspective Plan : No
Proposal Date : 1/5/2020 Work start date : 15/5/2020
Present status : Existing Proposed Status : Construction of Community Water Harvesting Ponds
Tech Sanction Details
Technical Sanction No. : 1725007/2020-2021/130304/TS Sanction Date : 3/6/2020
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
545074.91 161001.44 71.93 267.03 0 0 0 162000 0 706415.31
Financial Sanction Details
Financial\Administrative Sanction No: 1725007/2020-2021/130304/AS Financial\Administrative Sanction Date 3/6/2020
Fin. Sanc. Amt. (in Rs) NREGA:706703 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
707000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1(I) 0.5 Km. Lead990139.118555555556137727.37
2Site clearance, cutting grass, raking into heaps and removing off the premises33002.625457575757588664.01
3b (iii) Dense or hard soil for Tank Work1485134.187501683502199268.44
4c (iii) Hard moorum for Tank Work1980178.737752525253353900.75
5Loosing of hard soIl such as moorum etc. By ploughing (tractor ect.) the existing ground exceeding 30cm in depth as well as 10 sqm on plan including all running expanses of machine.9903.600181818181823564.18
6Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works )13578.363578.36
Total Activity 707000
S.NoMaterialQuantityUnit PriceTotal
10002-Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper0.018858.85
20084-Hire charges of Diesel truck - 9 tonne (without POL)36.96224282864.32
30367-Portland Cement0.02895511159.2679
40368-White cement 0.0004157446.2976
50983-Fine sand (zone IV)0.0471076.2550.58375
61235-Diesel oil99.792686785.856
75001-Mobil oil3.696182.9675.9984
87900-Modular common burnt clay bricks of class designation 7.5244.44.131009.372
9MR6001-Stone Aggregate(single size): 40 mm nominal size other than BT0.06552534.125
10MR6032-Snowcem/ durocem0.00072778919.4523
11MR6082-Stone Aggregate (Metal) 20mm nominal size (BT Metal) (Rate at quarry)0.02468216.368
12MR6089-Hire Charges for tractor with ploughing arrangement including running expanses and driver4.4557083154.14
Total Material 94800