S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 200 | 0.5 | 100 |
2 | Filling in plinth with sand under floors including watering, ramming, consolidating and dressing complete. | 54 | 638.8 | 34495.2 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 54 | 3194.2 | 172486.8 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 82 | 132.5 | 10865 |
5 | Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for | 1 | 5886 | 5886 |
6 | Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 30 Kms. and part there of upto 50 Kms. | 1 | 32508 | 32508 |
7 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 1 | 31400 | 31400 |
8 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Dense or hard soil | 1 | 22000 | 22000 |