State: MADHYA PRADESH District: BHIND Block: ATER Panchayat: SAKRAYA
Work Code: 1702001037/RC/22012034366065 (cc road gyan singh dhobi ke makan se antram ke darbaje tak)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2017-2018 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : No Perspective Plan : No
Proposal Date : 31/5/2017 Work start date : 20/10/2017
Present status : No Road Proposed Status : Constr of Cement Concrete Roads for Comm
Tech Sanction Details
Technical Sanction No. : 07/1037 Sanction Date : 31/5/2017
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
32550 184450 0 0 0 0 0 185000 0 217000
Financial Sanction Details
Financial\Administrative Sanction No: 06/1037 Financial\Administrative Sanction Date 31/5/2017
Fin. Sanc. Amt. (in Rs) NREGA:217000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
217000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Filling in plinth with sand under floors including watering, ramming, consolidating and dressing complete.40641.525660
2Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)453290.4148068
3False work for R.C.C. and P.C.C. work in plinth and foundation8013210560
4Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 50 Kms. and part there of upto 100 Kms.6066.333979.8
5Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 100 Kms.323009600
6Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 50metres and upto 1.5metre.-Dence or hard soil30011.23360
7Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making9031.22808
8Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work93.288.48238.88
9Excavating post holes (or similar holes) upto 0.5cum including getting out the excavated soil, than returning the soil as required in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering etc., disposing of-Dense or hard soil.42.2110.64667.32
Total Activity 217000
S.NoMaterialQuantityUnit PriceTotal
1CEMENT(BEGS)19530058500
2GITTI 20MM92.870265145.6
3mixer machin (perday)4565029250
4photographs1500500
5SAND62.6430.626955.56
6Transportation charges of mate120002000
7साईनबोर्ड 125002500
Total Material 185000