S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Dense or hard soil | 147.4 | 146.02 | 21523.348 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 59.9 | 3904.31 | 233868.169 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 43.8 | 3159.36 | 138379.968 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 110.4 | 156.78 | 17308.512 |
5 | Collection of approved soil having CBR not less than 5, including stacking at quarry. | 47.8 | 208.26 | 9954.828 |
6 | Transportation of metal | 47.8 | 143.39 | 6854.042 |
7 | Labour only for moorum, screening or binding material as per MOST 2004 clause 400.2.6 spreading on boulder or WBM coat as per MOST 2004 clause 404.2.7 | 47.8 | 73.67 | 3521.426 |