State: MADHYA PRADESH District: KHANDWA Block: BALADI Panchayat: BILLOD MAL
Work Code: 1725001006/WC/22012034597104 (जल संबर्धन जल संचयन पोंड हरेसिंग के खेत पास )
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2020-2021 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : No Perspective Plan : No
Proposal Date : 15/8/2020 Work start date : 25/11/2020
Present status : Non-existent Proposed Status : Constr of Brushwood Check Dam for Community
Tech Sanction Details
Technical Sanction No. : 1725001/2020-2021/435751/TS Sanction Date : 4/12/2020
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
518536.68 588057.74 6308.06 19771.06 0 0 0 615000 0 1132673.54
Financial Sanction Details
Financial\Administrative Sanction No: 1725001/2020-2021/435751/AS Financial\Administrative Sanction Date 9/12/2020
Fin. Sanc. Amt. (in Rs) NREGA:1132961 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
1133000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1(b) C.C. 1:3:6 (1cement, 3sand, 6metal)156.083162.78472578165493647.44
2Plum cement concrete 1:3:6 with 75% graded metal of 40mm size and 25% plums of 150mm size.242317.3955617.36
3Centering and shuttering including strutting , propping etc. and removal of form work for P.C.C. work in foundation, footing, bases for column264.16160.51972289521542402.89
4(XV) 10 Km. Lead172.09233.04009529897140103.87
5(XIII) 8 Km. Lead84.68188.77491733585315985.46
6Site clearance, cutting grass, raking into heaps and removing off the premises20002.625465250.92
7b (iii) Dense or hard soil for Tank Work41.25134.1873939393945535.23
8c (iii) Hard moorum for Tank Work47.2178.7377118644078436.42
9a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work90.45568.94825870646851461.37
10(b) Dense or hard soil1800146.027538888889262849.57
11(c) Hard moorum640173.800984375111232.63
12Spreading dressing, breaking of clods of ploughed earth upto 20m lead and lift upto 1.5m disposed soil to be leveled and neatly dressed.50073.6689436834.47
13Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works )13603.483603.48
Total Activity 1133000
S.NoMaterialQuantityUnit PriceTotal
10002-Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper18.317588516210.9875
20084-Hire charges of Diesel truck - 9 tonne (without POL)8.4271224218893.5582
30367-Portland Cement37.42545511206251.3794
40368-White cement 0.0004157446.2976
50983-Fine sand (zone IV)79.82221076.2585908.64275
61235-Diesel oil139.6738689497.8184
75001-Mobil oil4.9704182.9909.08616
87900-Modular common burnt clay bricks of class designation 7.5244.44.131009.372
9MR6001-Stone Aggregate(single size): 40 mm nominal size other than BT119.513752562744.6925
10MR6002-Shingles, Graval, Pabbles, Plums 150mm nominal size (Rate@Quarry)6157.47944.82
11MR6032-Snowcem/ durocem0.00072778919.4523
12MR6082-Stone Aggregate (Metal) 20mm nominal size (BT Metal) (Rate at quarry)37.48268225562.724
13MR6091-WOOD-Kail wood 2nd class0.943415825.614929.87104
Total Material 443000