Govt. of India
Ministry of Rural Development
Department of Rural Development
The Mahatma Gandhi National Rural Employment Guarantee Act 26-Sep-2024 11:19:07 PM 
Back  
State: MADHYA PRADESH District: KHANDWA Block: PANDHANA Panchayat: SAROLA
Work Code: 1725007067/RC/552 (ग्रेवल मार्ग निर्माण रघुनाथ के खेत से टूण्‍टी इमली के खेत पर/ सारोला )
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2012-2013 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 14/4/2012 Work start date : 2/5/2012
Present status : Earthern road Proposed Status : Earthern road
Tech Sanction Details
Technical Sanction No. : 64**. Sanction Date : 1/5/2012
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
348000 137000 0 0 0 0 0 137000 0 485000
Financial Sanction Details
Financial\Administrative Sanction No: 02**. Financial\Administrative Sanction Date 2/5/2012
Fin. Sanc. Amt. (in Rs) NREGA:485000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
485000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil113.573.48330.9
2Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)100.093002.1300480.189
3Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal)000
4Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used60.09108.76531.783
5False work for R.C.C. and P.C.C. work in plinth and foundation450.5147.466403.7
6Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide)20006.312600
7Collection of approved soil having CBR not less then 12, including stacking at quarry.100.18105.310548.954
8Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 100.181.5150.27
9Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 160.0936.55843.285
10Transportation of metal 150.0720430614.28
11Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.140.24133.7618758.5024
12Labour only for moorum, screening or binding material as per MOST 2004 clause 400.2.6 spreading on boulder or WBM coat as per MOST 2004 clause 404.2.7150.1821.33198.834
13work charge12100021000
Total Activity 485000
S.NoMaterialQuantityUnit PriceTotal
1Display board110001000
2Drinking Water Facilities120002000
3Gravel or moorum50120060000
4HumePipes225005000
5Tansportation of water20120024000
6Transportation of hard moorum20100020000
7रोलर15165024750
Total Material 137000