S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 2400 | 3.4 | 8160 |
2 | Contingency | 1 | 401 | 401 |
3 | Collection of approved soil having CBR not less than 5, including stacking at quarry. | 594 | 75.4 | 44787.6 |
4 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 594 | 114.3 | 67894.2 |
5 | Labour only for moorum, screening or binding material as per MOST 2004 clause 400.2.6 spreading on boulder or WBM coat as per MOST 2004 clause 404.2.7 | 594 | 19.7 | 11701.8 |
6 | Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN | 144 | 81.7 | 11764.8 |
7 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work | 573.6 | 67.8 | 38890.08 |