S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Labour only for item no. 63.09.30 | 250 | 13.186 | 3296.5 |
2 | (a) Dense or hard soil (PT/60/60) | 112.32 | 159.736823361823 | 17941.64 |
3 | Citizen Information Board of size 0.6 meter x 0.9 meter ( Individual works ) | 1 | 2249.42 | 2249.42 |
4 | Filling dug pits with manure/compost for dug-pit size 0.60x0.60x0.60 m (using Manure and Excavated earth for filling) | 400 | 11.978 | 4791.2 |
5 | Filling dug pits of size 0.6 x 0.6 x 0.6 m using excavated earth, in any year except first year | 120 | 7.6 | 912 |
6 | (VIII) Anar plant (layering) | 520 | 38.194 | 19860.88 |
7 | Watering, Weeding, Hoeing, Training, Pruning, Mulching, Stacking, Bunding, along sides (thala making), filling the soil in and around the plant spraying insecticide/pesticide, putting required manure and fertilizer etc, when plant planted 3m x 3m full supervision (only in case of survival more than 85%) in first year. | 400 | 134.694875 | 53877.95 |
8 | Watering, Weeding, Hoeing, Training, Pruning, Mulching, Stacking, Bunding, along sides (thala making), filling the soil in and around the plant spraying insecticide/pesticide, putting required manure and fertilizer etc, when plant planted 3m x 3m full supervision (only in case of survival more than 95%) in second year. | 400 | 100.868325 | 40347.33 |
9 | Watering, Weeding, Hoeing, Training, Pruning, Mulching, Stacking, Bunding, along sides (thala making), filling the soil in and around the plant spraying insecticide/pesticide, putting required manure and fertilizer etc, when plant planted 3m x 3m full supervision (only in case of survival more than 100%) in third year | 400 | 62.222325 | 24888.93 |
10 | (I) 0 to 10 km | 520 | 1.25 | 650 |
11 | Maintenance of barbed wire fencing | 500 | 1.311 | 655.5 |