S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 750 | 1.8 | 1350 |
2 | Labour only for lime mortar & lime surkhi mortar | 538 | 5 | 2690 |
3 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil | 525 | 70.8 | 37170 |
4 | Transportation of metal | 300 | 180.1 | 54030 |
5 | Unloading of metal in truck, dumper etc. | 445 | 42.93 | 19103.85 |
6 | Collection of soft moorum including stacking at quarry. | 300 | 125.2 | 37560 |