State: MADHYA PRADESH District: DAMOH Block: JABERA Panchayat: PONDI MANGARH
Work Code: 1711006064/IF/1289 (कपि‍ल धारा कूप र्नि‍माण कार्य/ डब्‍बलि‍या जीवन / प)
Work Category: Drought Proofing
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2011-2012 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Perspective Plan :
Proposal Date : 19/5/2011 Work start date : 30/7/2011
Present status : Not Exist Proposed Status : Well
Tech Sanction Details
Technical Sanction No. : 153j Sanction Date : 19/5/2011
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
113800 52200 0 0 0 0 0 52200 0 166000
Financial Sanction Details
Financial\Administrative Sanction No: 3j Financial\Administrative Sanction Date 30/7/2011
Fin. Sanc. Amt. (in Rs) NREGA:166000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
166000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Dag-beling-Double spade "v" shaped stroke 100mm deep8000.5400
2Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead19821.94336.2
3Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m132.7235.84751.376
4Labour only for item no. 04048.129.8241.38
5Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)1.541860.32864.862
6Random / uncoursed rubble masonry in plinth and foundation with mud mortar including levelling at plinth level.62.8711043.665612.1756
7Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:8 (1cement, 8sand)3.551670.85931.34
8Labour only for item no.05180.953120.92964.855
9Add extra for brick masonry circular in plan, I/c wells to a mean radius not exceeding 6m (Such as well stening and other similar type of works)67.11265.517817.705
10Add to item no.0605 and 0609 for well staining-For every 3meter up to 15 meter depth.98.65172.316997.395
11Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:3 (1cement, 3sand)-Ruled pointing20.1585.11714.765
12Collection of hard metal other then black trap basalt and granite for road works (without blasting) including stacking as per MOST 1995, clause 400.2.5-Grading - 1 (Size ranging from 90 mm to 45 mm)8.1240.61948.86
13Labour only for boulder soling hand packed excluding consolidation.8.1106.2860.22
14Labour only for spreading, hand packing, and levelling to gradient and required camber as per MOST 2004 clause 404.3.3 of metal, grade-1 As per MOST 2004 clause 400.2.5 including dressing.8.172.9590.49
15Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil42.3946.61975.374
16Earth work for well excavation including disposal of excavated soil lead upto 20 m. & lift upto 1.5 m., disposed soil to be levelled and neatly dressed. Loose or soft soil. Li1.5 m. to 2.00 m.ft from14.1366.6941.058
17Earth work for well excavation-Soil lift from 2.00 m. to 2.50 m.14.1371.51010.295
18Earth work for well excavation-soil lift from 2.50 m. to 3.00 m.14.1376.41079.532
19Earth work for well excavation-Soil lift from 3.00 m. to 3.50 m.14.1381.31148.769
20Earth work for well excavation-Soil lift from 5.50 m. to 6.00 m.14.13124.31756.359
21Earth work for well excavation-Soil lift from 3.50 m. to 4.00 m.14.1386.21218.006
22Earth work for well excavation-Soil lift from 4.00 m. to 4.50 m.14.1391.11287.243
23Earth work for well excavation-Soil lift from 4.50 m. to 5.00 m.14.13961356.48
24Earth work for well excavation-Soil lift from 5.00 m. to 5.50 m.14.13100.91425.717
25Earth work for well excavation-Soil lift from 6.00 m. to 6.50 m.14.13130.71846.791
26Earth work for well excavation-Soil lift from 6.50 m. to 7.00 m.14.13137.11937.223
27Earth work for well excavation-Soil lift from 7.00 m. to 7.50 m.14.13143.52027.655
28Earth work for well excavation-soil lift from 7.50 m. to 8.00 m.14.13149.92118.087
29Earth work for well excavation-Soil lift from 8.00 m. to 8.50 m.14.13288.24072.266
30Earth work for well excavation-Soil lift from 8.50 m. to 9.00 m.14.132974196.61
31Earth work for well excavation-Soil lift from 9.00 m. to 9.50 m.14.13305.84320.954
32Earth work for well excavation-Soil lift from 9.50 m. to 10.00 m.14.13314.64445.298
Total Activity 166000
S.NoMaterialQuantityUnit PriceTotal
120 M.M. METAL0.5650325
240 M.M. METAL1375375
3Blasting (No)30601800
4Cement(bori)153004500
5desal pump rent74002800
6Display board120002000
7First Aid Box1500500
8MASON (PERDAY)7022515750
9Masonry Stone62.9830018894
10Photo copy503150
11Photograph850400
12sand (t)2.56250640
13TRAINSPORT CHARGE140004000
Total Material 52200