S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 3682 | 3682 |
2 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 4465 | 7.02 | 31344.3 |
3 | Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 5 Kms. and part there of upto 10 Kms. | 2788.28 | 213.91 | 596440.9748 |
4 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 2509.8 | 17.44 | 43770.912 |
5 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 2788.28 | 19.31 | 53841.6868 |
6 | Compaction of soil for construction of subgrade & earthen shoulders with approved transported material collected and stacked at site, i/c spreading, making 4% camber and required gradient by tractor mounted grader or labourers, watering at OMC and compact | 300.8 | 36.63 | 11018.304 |
7 | Construction of hard shoulder as per clause 407 of specifications for rural roads (MORD), with soil having CBR value not less than 12, inclusive of all leads and lifts, providing 4-5% camber by tractor mounted grader or labourers, watering at OMC and comp | 300.8 | 292.53 | 87993.024 |
8 | Construction of gravel base course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more to bring the material in appropriate grading confirming to A or B or C of Table 2.1of IRC:SP:77-2008 having CBR not less | 634.5 | 548.57 | 348067.665 |
9 | Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP: | 141 | 468.97 | 66124.77 |
10 | Lossening of hard soil by ploughing the existing gound | 8991.34 | 79.1 | 711214.994 |
11 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 8991.34 | 3.6 | 32368.824 |