S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Contingency | 1 | 812 | 812 |
2 | Site clearance, cutting grass, raking into heaps and removing off the premises | 1.4 | 600 | 840 |
3 | Earth work in rough excavation,filling excavated earth into depressions on banking as directed ,top surface to be levelled and neatly dressed.-Loose or soft soil | 74.9 | 270 | 20223 |