State: MADHYA PRADESH District: BHIND Block: ATER Panchayat: BIRGANVANRANI
Work Code: 1702001032/RC/22012034287800 (Antririk Mary Norman main road to pathak tola)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2015-2016 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 14/4/2015 Work start date : 28/10/2015
Present status : No Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 111 n Sanction Date : 20/10/2015
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
304000 168000 0 0 0 0 0 168000 0 472000
Financial Sanction Details
Financial\Administrative Sanction No: 3/111n Financial\Administrative Sanction Date 25/10/2015
Fin. Sanc. Amt. (in Rs) NREGA:472000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
472000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard125002500
2Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.8104.43564
3Stacking and boxing.-Moorum or sand5415810
4Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.1182000182000
5Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN54713834
6Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making2072.2531.264654.2
7Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work2072.2588.4183186.9
8Collection of hard moorum including stacking at quarry.54142.57695
9R C C Pole Fixing only5487.74735.8
10contingency11818218182
Total Activity 472000
S.NoMaterialQuantityUnit PriceTotal
1Compaction of Earth Work2072.2531.264654.2
2Compaction of GSB54713834
3contigency170007000
4Transpotation Charges19250092500
Total Material 168000