S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Contingency | 15806.26 | 1 | 15806.26 |
2 | Dag-beling-Single spade stroke minimum 75mm deep | 280 | 0.2 | 56 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 2837.8 | 98 | 278104.4 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 124.8 | 112 | 13977.6 |
5 | Stacking without boxing.-Puddle earth, moorum, sand or kankar | 10.5 | 77.7 | 815.85 |
6 | Transportation rates for Masonry stone. | 203.4 | 83.3 | 16943.22 |
7 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 219.06 | 141.4 | 30975.084 |
8 | Loading of metal in truck, dumper etc. | 26.28 | 77.7 | 2041.956 |
9 | Unloading of metal in truck, dumper etc. | 13.14 | 77.7 | 1020.978 |
10 | Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing. | 34 | 77.7 | 2641.8 |
11 | Collection of hard moorum including stacking at quarry. | 118.3 | 77.7 | 9191.91 |
12 | Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 20metres and upto 1.5metre.-Dense or hard soil. | 518 | 11.6 | 6008.8 |