State: MADHYA PRADESH District: DHAR Block: MANAWAR Panchayat: Rajukhedi
Work Code: 1722/WC/22012034518202 (Nistar talab kateli khodri Rajukhedi)
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2019-2020 Execution Level : ZP
Execution Agency : Rural Engineering Services(04004) Work Status : Approve
Included in Annual Plan : No Perspective Plan : No
Proposal Date : 2/10/2019 Work start date : 8/1/2020
Present status : Non-existent Proposed Status : Constr of Earthen Check Dam for Community
Tech Sanction Details
Technical Sanction No. : 22/186 Sanction Date : 10/12/2019
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
2762000 1811000 0 0 0 0 0 1811000 0 4573000
Financial Sanction Details
Financial\Administrative Sanction No: 20/r Financial\Administrative Sanction Date 4/1/2020
Fin. Sanc. Amt. (in Rs) NREGA:4573000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
4573000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Site clearance, cutting grass, raking into heaps and removing off the premises4516.5313549.5
2Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal)37.462562.595991.25
322cm thick dry stone pitching (without quarry spalls) with individual stone of 22cm depth and minimum size 0.0141915.23165316012.95
4Transportation of metal 5483.16172.4945296.784
5Transportation of metal 10181.1183.161864770.276
6FOR EARTHEN DAM - Puddle filling of good clay including lead upto 50m including mixing watering and kneeding by tamping ramming and laying etc.1092.39474517792.86
7FOR EARTHEN DAM - Construction of rock toe in earthen embankments including laying and hand packing, dressing, wedging and finishing over surface with.-Boulders771.53574.6443321.138
8Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed2814.1352.7148304.651
9FTSC- Field supervision charges2276100227600
Total Activity 4573000
S.NoMaterialQuantityUnit PriceTotal
122 CM Piching Bolder Supplyes1915.2336.970671.987
2Boulder Transportation771.53293226058.29
3Contengency1620100162000
4Lead of Casing Soil 0.50 Km9635.1773.26705872.5542
5Lead of Hearting Soil4862.5268.96335319.3792
6Transportation of puddle earth1092.39279.98305847.3522
7बोर्ड150005000
Total Material 1811000