S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 8889 | 1.8 | 16000.2 |
2 | Dag-beling-Single spade stroke minimum 75mm deep | 5000 | 0.3 | 1500 |
3 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m | 1233 | 52.7 | 64979.1 |
4 | Collection of approved soil having CBR not less than 5, including stacking at quarry. | 2657 | 52.7 | 140023.9 |
5 | Collection of approved soil having CBR not less then 12, including stacking at quarry. | 417 | 52.7 | 21975.9 |
6 | Transportation of metal | 2962 | 105 | 311010 |
7 | Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-600mm dia | 5 | 4121 | 20605 |
8 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 1389 | 21.6 | 30002.4 |
9 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 2814 | 23.1 | 65003.4 |
10 | Compaction of hard shoulder collected at site, i/c making 4-5% camber by tractor mounted grader or labourers, watering at OMC and compacting with 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7) | 499 | 40.1 | 20009.9 |
11 | Construction of gravel base course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more to bring the material in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clau | 625 | 576 | 360000 |
12 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed. | 2 | 7000 | 14000 |
13 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed. | 4 | 4504.5 | 18018 |
14 | Cautionary, mandator, informatory, direction and place indentification signs | 6 | 3082 | 18492 |
15 | Kilometre Stone Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703 With Reinforced cement concrete (i) 5th Kilometre Stone (precast) (ii) Ordinary Kilometer Stone (Precast) (iii) 200 m stone (precast) | 10 | 402 | 4020 |