S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 20.25 | 882 | 17860.5 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 15.19 | 3307.4 | 50239.406 |
3 | False work for R.C.C. and P.C.C. work in plinth and foundation | 30 | 147.8 | 4434 |
4 | Coursed rubble masonry second sort in plinth and foundation.-In Cement mortar 1:8 (1cement, 8sand) | 67.5 | 2082.1 | 140541.75 |
5 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 150 | 127.6 | 19140 |
6 | Cutting out cracked of roof terrace to V-Section, cleaning out and filling solidly with a hot mixture of bitumen and clean dry sand slurry 1:1 (1 by weight) | 15.19 | 548 | 8324.12 |
7 | Transportation of metal | 12.9094 | 288.7 | 3726.94378 |
8 | Transportation of sand | 35.226 | 377.73 | 13305.91698 |
9 | Transportation rates for Masonry stone. | 67.5 | 257.18 | 17359.65 |
10 | Transportation rates for Boulders, Laterite, rubble pitching stones and excavated hard rock. | 18.63 | 183.7 | 3422.331 |
11 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 162 | 52.7 | 8537.4 |
12 | contingency | 1 | 9107.98224 | 9107.98224 |