State: MADHYA PRADESH District: KHARGONE Block: BHAGVANPURA Panchayat: KHAPAR JAMLI
Work Code: 1724008056/WC/12172 (कपिलधारा कुप निर्माण कार्य टेटया घुच्‍या (Est. 1.6)
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2012-2013 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Perspective Plan :
Proposal Date : 5/4/2012 Work start date : 20/10/2012
Present status : Non-existent Proposed Status : Mini Percolation tank
Tech Sanction Details
Technical Sanction No. : 23(13-) Sanction Date : 12/4/2012
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
99600 66400 0 0 0 0 0 66400 0 166000
Financial Sanction Details
Financial\Administrative Sanction No: 08(13-) Financial\Administrative Sanction Date 20/10/2012
Fin. Sanc. Amt. (in Rs) NREGA:166000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
166000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:2:4 (1cement, 2sand, 4graded stone aggregate 20 mm nominal size)6.333119.419745.802
2False work for R.C.C. and P.C.C. work in plinth and foundation126.612615951.6
3Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Cold twisted / Hot rolled deformed / Thermo mechanicaly treated steel bars200.661.512336.9
4Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work66.23108.27166.086
5Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard moorum for Well Work66.23130.78656.261
6Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Disintegrated or soft rock (not requiring blasting) for Tank Work71.22386.427519.408
7Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard rock requiring blasting for Tank Work105.34704.574212.03
Total Activity 166000
S.NoMaterialQuantityUnit PriceTotal
120 M.M. METAL.2.530007500
2Blasting Holas1908015200
3Cement(bori)4131012710
4Centering and Shuttering124.6708722
5contergency143574357
6IRON SARIYA200.65511033
7Karigar Semi Skilled Labour162403840
8Sand215003000
Total Material 66400