S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Dense or hard soil | 135 | 68.2 | 9207 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 4.6 | 3249.2 | 14946.32 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal) | 13.5 | 2074.3 | 28003.05 |
4 | Coursed rubble masonry second sort in plinth and foundation.-In Cement mortar 1:6 (1cement, 6sand) | 27.6 | 2225.3 | 61418.28 |
5 | TRANSPORTATION OF MATERIAL | 1 | 12662 | 12662 |
6 | Pointing on CR masonry with cement mortar 1:4(1cement, 4sand)-Flush pointing | 90 | 69.4 | 6246 |