Govt. of India
Ministry of Rural Development
Department of Rural Development
The Mahatma Gandhi National Rural Employment Guarantee Act 28-Sep-2024 12:05:10 AM 
Back  
State: MADHYA PRADESH District: REWA Block: SIRMOUR Panchayat: JHALWAR
Work Code: 1713003033/RC/22012034232331 (खेत सडक मुख्‍य मार्ग से जगुआ तालाब तक TS 900)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2013-2014 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 1/1/2014 Work start date : 1/4/2014
Present status : Gravel Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 900/36/1 Sanction Date : 6/1/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
470000 366000 0 0 0 0 0 366000 0 836000
Financial Sanction Details
Financial\Administrative Sanction No: 18/36/1 Financial\Administrative Sanction Date 1/4/2014
Fin. Sanc. Amt. (in Rs) NREGA:836000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
836000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard115001500
2Site clearance, cutting grass, raking into heaps and removing off the premises49801.67968
3Work charge12500025000
4Transportation of metal 124292.1114388.2
5Transportation of metal 1279.2699.6127414.296
6Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-300mm dia2.5309.4773.5
7Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making952.521.520478.75
8Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor1279.2626.233516.612
9Compaction of hard shoulder collected at site, i/c making 4-5% camber by tractor mounted grader or labourers, watering at OMC and compacting with 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7)195.2639.67732.296
10Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP:89.5578.351757.85
11Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.952.581.277343
12Collection of puddle earth including stacking at quarry1242112.8140097.6
13Collection of hard moorum including stacking at quarry.270130.835316
141902 Transportion of metal1119000119000
15Labour difference in case of old SoR2.52920073000
Total Activity 836000
S.NoMaterialQuantityUnit PriceTotal
1contigency12600026000
2hume pipe10779677960
3Rolling Earth & moorum180063.36114048
4Transportation of GSB90088.2579425
5Transportation of Water90023.5621204
6Transpotation Charges18517332005
7रोलर90016.815120
Total Material 366000