S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 837.5 | 6.54194626865672 | 5478.88 |
2 | (a) Other then black trap Basalt or granite | 73.45 | 298.858407079646 | 21951.15 |
3 | (a) Consolidation of Moorum /earth work (rate for 1Cum. of Moorum /earth work) | 813.9 | 2.3512470819511 | 1913.68 |
4 | (XI) 6 Km. Lead | 73.45 | 261.068754254595 | 19175.5 |
5 | (XIV) 9 Km. Lead | 357.5 | 199.264111888112 | 71236.92 |
6 | (XXV) 30 Km. Lead | 302.5 | 366.695008264463 | 110925.24 |
7 | (III) 1.5 Km. Lead | 153.9 | 104.142949967511 | 16027.6 |
8 | (a) Boulders | 75 | 570.8252 | 42811.89 |
9 | For earthen dam - puddle filling of good clay including lead upto 20 meter including mixing, watering & kneading by tamping , ramming & laying etc. | 153.9 | 421.809096816114 | 64916.42 |
10 | Hearting, casing/cut off filling soil etc.
At optimum moisture content to achieve maximum dry density by mechanical sheep foot roller/ vibratory compacters including watering, required leads and lifts and material etc. complete. | 786.4 | 21.7465412004069 | 17101.48 |
11 | a (iii) Loose or soft soil for Tank Work | 39.83 | 99.3936731107206 | 3958.85 |
12 | b (iii) Dense or hard soil for Tank Work | 302.5 | 134.187504132231 | 40591.72 |
13 | c (iii) Hard moorum for Tank Work | 373.7 | 178.73775755954 | 66794.3 |
14 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 24.3 | 568.948148148148 | 13825.44 |