S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 2820 | 6.54194680851064 | 18448.29 |
2 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 111.51 | 3162.8860191911 | 352693.42 |
3 | Plum cement concrete 1:3:6 with 75% graded metal of 40mm size and 25% plums of 150mm size. | 16 | 2317.39 | 37078.24 |
4 | Centering and shuttering including strutting , propping etc. and removal of form work for P.C.C. work in foundation, footing, bases for column | 226.16 | 160.519720551822 | 36303.14 |
5 | (XV) 10 Km. Lead | 160 | 233.046875 | 37287.5 |
6 | (XIII) 8 Km. Lead | 84.68 | 188.774917335853 | 15985.46 |
7 | b (iii) Dense or hard soil for Tank Work | 2264.5 | 134.187498344005 | 303867.59 |
8 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 66.3 | 568.94826546003 | 37721.27 |
9 | Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works ) | 1.2 | 3603.48333333333 | 4324.18 |