Govt. of India
Ministry of Rural Development
Department of Rural Development
The Mahatma Gandhi National Rural Employment Guarantee Act 26-Sep-2024 11:15:17 PM 
Back  
State: MADHYA PRADESH District: KHANDWA Block: CHHAIGAON MAKHAN Panchayat: BADIYA GYASUR
Work Code: 1725006005/IF/09 (कपिलधारा कूप सह मेढ बंधान कार्य लालसिंह लक्ष्‍मणसि)
Work Category: Drought Proofing
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2011-2012 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Perspective Plan :
Proposal Date : 1/5/2011 Work start date : 10/5/2011
Present status : Existing Proposed Status : Well
Tech Sanction Details
Technical Sanction No. : 0092 Sanction Date : 10/5/2011
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
95000 55000 0 0 0 0 0 55000 0 150000
Financial Sanction Details
Financial\Administrative Sanction No: ba09 Financial\Administrative Sanction Date 10/5/2011
Fin. Sanc. Amt. (in Rs) NREGA:150000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
150000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil000
2Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil000
3Extra rates for quantities of work executed. In or under water or in foul condition (extra rate for the main item concerned is allowed on account of slow progress of works)65.87127.238380.6401
4Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead20036.67320
5Labour only for item no.040280302400
6Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:1.5:3 (1cement, 1.5sand, 3graded stone aggregate 20 mm nominal size)5.52557.614066.8
7False work for lintels slabs, columns, walls, sills, chhajjas balconies, beams, stair cases or ornamental moulded work, curved surface etc. cast in situ including all lead and lift88155.913719.2
8False work for R.C.C. and P.C.C. work in plinth and foundation000
9Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Mild steel and Medium tensile steel bars15051.77755
10Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil38.4175.32892.273
11Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Hard Moorum57.2297.85596.116
12Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Disintegrated or soft rock (not requiring blasting)000
13Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Hard rock requiring blasting.164450.4573873.8
14Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Hard rock requiring chiselling (where blasting is prohibited)31.79221.77047.843
15Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work4074.92996
16Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed-Hard moorum for Road Work4076.33052
17work charge000
Total Activity 150000
S.NoMaterialQuantityUnit PriceTotal
110 mm -  M.S. rod145004500
220 M.M. METAL7.43761.55657.945
340 mm Metal120002000
4Blasting Holas1757012250
5Cement1250250
6Cement(bori)3053610980
7Centering and Shuttering100888800
8Centring & Shuttering1500500
9CONTANGANCY316004800
10Display board115001500
11PhotoCopy & Stationary155023100
12photographs12020
13R.R. stone (granite)18080
14Sand120002000
15sand (t)6565.263391.56
16STEEL120506000
17xerox111
Total Material 65900