S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 320.29 | 3123.27578132318 | 1000354 |
2 | Plum cement concrete 1:3:6 with 75% graded metal of 40mm size and 25% plums of 150mm size. | 56 | 2273.73267857143 | 127329.03 |
3 | False work for R.C.C. and P.C.C. work in plinth and foundation. | 579.5 | 159.51142364107 | 92436.87 |
4 | (d) 2.0 Km. Lead | 279.56 | 124.245957933896 | 34734.2 |
5 | (IV) 2.0 Km. Lead | 48.72 | 108.564449917898 | 5289.26 |
6 | (V) 2.5 Km. Lead | 146.16 | 115.53297755884 | 16886.3 |
7 | Site clearance, cutting grass, raking into heaps and removing off the premises | 432 | 2.43201388888889 | 1050.63 |
8 | b (iii) Dense or hard soil for Tank Work | 178.6 | 124.3 | 22199.98 |
9 | c (iii) Hard moorum for Tank Work | 84.8 | 165.567570754717 | 14040.13 |
10 | a (ii) Disintegrated or soft rock (not requiring blasting) for Well Work | 149.7 | 526.686239144957 | 78844.93 |
11 | Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works ) | 1 | 3516.31 | 3516.31 |