S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 370 | 0.3 | 111 |
2 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 20.81 | 871 | 18125.51 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 8.33 | 3267.64 | 27219.4412 |
4 | Random / uncoursed rubble masonry in plinth and foundation with mud mortar including levelling at plinth level. | 192.86 | 983.7 | 189716.382 |
5 | Steel work welded in built up sections, framed work, including cutting hoisting fixing in position in gratings, frames, guard bars, ladders, railing, brackets and similar works & trusses and trussed purlins up to 25m span and 15 m over all height | 100 | 65.9 | 6590 |
6 | Pointing on CR masonry with cement mortar 1:4(1cement, 4sand)-Flush pointing | 666 | 62.8 | 41824.8 |
7 | Transportation of metal | 9.75 | 200.61 | 1955.9475 |
8 | Transportation of sand | 7.47 | 200.61 | 1498.5567 |
9 | Transportation rates for Masonry stone. | 192.86 | 227.5 | 43875.65 |
10 | Transportation rates for Bricks, kanker, stone chips shingle & excavated materials in disintegrated rock & soft rock. | 87.87 | 101.61 | 8928.4707 |
11 | Transportation rates for Boulders, Laterite, rubble pitching stones and excavated hard rock. | 20.81 | 111.17 | 2313.4477 |
12 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 3.16 | 220.9 | 698.044 |
13 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Dense or hard soil | 104.06 | 95 | 9885.7 |
14 | contingency | 1 | 22264.0502 | 22264.0502 |