S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Disintegrated or soft rock (not requiring blasting) | 59.984 | 363.856528407575 | 21825.57 |
2 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m | 47.927 | 67.0073236380328 | 3211.46 |
3 | (a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 181.673 | 4237.92489803108 | 769916.53 |
4 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 79.16 | 3467.9885042951 | 274525.97 |
5 | Providing and laying in foundation, plinth and under floors cement concrete with 20mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work ( if 20 mm metal is used in place of 40mm metal in item number 04.13 & 04.15)
(a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 13.66 | 4408.24597364568 | 60216.64 |
6 | (b) CC 1:1.5:3 (1 cement, 1.5 sand, 3 graded stone aggregate 20mm nominal size) | 14.607 | 6234.47319778189 | 91066.95 |
7 | False work for R.C.C. and P.C.C. work in plinth and foundation. | 408.6 | 191.199339207048 | 78124.05 |
8 | (b) Cold twisted / Hot rolled deformed / Thermo mechanicaly treated steel bars | 362.768 | 90.3844605918934 | 32788.59 |
9 | (b) 1000 mm dia. | 15 | 5106.56733333333 | 76598.51 |
10 | Construction of hard shoulder as per clause 407 of specifications for rural roads (MORD), with soil having CBR value not less than 12, inclusive of all leads and lifts, providing 4-5% camber by tractor mounted grader or labourers, watering at OMC and compacted by 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7), i/c all leads and lifts of materials etc. complete. | 73.018 | 286.084527102906 | 20889.32 |
11 | (b) Dense or hard soil | 71.982 | 169.853018810258 | 12226.36 |
12 | (c) Hard moorum | 107.973 | 202.157946894131 | 21827.6 |