S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Contingency | 1 | 15364.931 | 15364.931 |
2 | Dag-beling-Single spade stroke minimum 75mm deep | 200 | 0.2 | 40 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 10.13 | 2922.4 | 29603.912 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 15 | 2010.4 | 30156 |
5 | False work for R.C.C. and P.C.C. work in plinth and foundation | 30 | 128.6 | 3858 |
6 | Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:8 (1cement, 8sand) | 36 | 1645.3 | 59230.8 |
7 | Pointing on CR masonry with cement mortar 1:4(1cement, 4sand)-Raised and cut pointing | 110 | 90.2 | 9922 |
8 | Transportation of 20 MM metal | 8.61 | 410.4 | 3533.544 |
9 | Transportation of sand | 26.88 | 172.26 | 4630.3488 |
10 | Transportation rates for Masonry stone. | 36 | 453.04 | 16309.44 |
11 | Transportation rates for Bricks, kanker, stone chips shingle & excavated materials in disintegrated rock & soft rock. | 13.8 | 212.4 | 2931.12 |
12 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 5.97 | 126.54 | 755.4438 |
13 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Dense or hard soil | 97.5 | 88.3 | 8609.25 |