State: MADHYA PRADESH District: KHANDWA Block: BALADI Panchayat: SEMRUDH RAIYAT
Work Code: 1725001035/DW/22012034294745 (NIRMAL NIR PEYJAL KUP - NAVIN PANCHAYAT KE PAS )
Work Category: Drinking Water
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2016-2017 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : No Perspective Plan : No
Proposal Date : 2/10/2016 Work start date : 20/1/2017
Present status : Not Exist Proposed Status : DUGWELLS
Tech Sanction Details
Technical Sanction No. : 412/016 Sanction Date : 20/1/2017
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
245000 200000 0 0 0 0 0 200000 0 445000
Financial Sanction Details
Financial\Administrative Sanction No: 65/016 Financial\Administrative Sanction Date 27/1/2017
Fin. Sanc. Amt. (in Rs) NREGA:445000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
445000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Site clearance, cutting grass, raking into heaps and removing off the premises122402880
2Mud Mortar93977.7735799.93
3Extra rates for quantities of work executed. In or under water or in foul condition (extra rate for the main item concerned is allowed on account of slow progress of works)12050860960
4Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)20.583766.577514.57
5False work for R.C.C. and P.C.C. work in plinth and foundation167.526444220
6Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Mild steel and Medium tensile steel bars90474230
7Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Cold twisted / Hot rolled deformed / Thermo mechanicaly treated steel bars36166.423970.4
8Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil98.2519.231889.3475
9Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Hard rock requiring blasting.350447156450
10Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Hard rock requiring chiselling (where blasting is prohibited)691258625
11Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-oose or soft soil for Well Work15218628272
Total Activity 445000
S.NoMaterialQuantityUnit PriceTotal
1Balsting Work25015037500
2Cement15231047120
3Centering and Shuttering21180037800
4Display board120002000
5Photocopy & staionary110001000
6PhotoCopy & Stationary000
7Sand8250020000
8STEEL5520026000
9TRAINSPORT CHARGE7150010500
10गिटटी 20 एम एम5350017500
Total Material 200000