State: MADHYA PRADESH District: BHIND Block: ATER Panchayat: DHARAI
Work Code: 1702001041/RC/22012034231077 (Internal road Bamba to Ramesh House)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2014-2015 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 15/8/2014 Work start date : 4/10/2014
Present status : No Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 8007 Sanction Date : 11/9/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
229000 135000 0 0 0 0 0 135000 0 364000
Financial Sanction Details
Financial\Administrative Sanction No: 03/8007 Financial\Administrative Sanction Date 26/9/2014
Fin. Sanc. Amt. (in Rs) NREGA:364000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
364000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard120002000
2Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.29254.412870
3Chain and compass survey.-Canals/Roads0.325636206.7
4Fly levelling for fixing temporary bench marks.-Above 15 m interval0.325477155.025
5Levelling - Headwork.-Above 15 m interval0.325508165.1
6Stacking and boxing.-Moorum or sand16911.51943.5
7Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.13900039000
8Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN1697111999
9Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making214131.266799.2
10Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work214188.4189264.4
11Collection of hard moorum including stacking at quarry.169142.524082.5
12R C C Pole Fixing only16987.714821.3
13contingency11414
Total Activity 364000
S.NoMaterialQuantityUnit PriceTotal
1Compaction of Earth Work214131.266799.2
2Compaction of GSB1697111999
3Compaction of Selected soil132.732.7
4Convergence Amount120002000
5Kilometre Stone (200 M)1334334
6Kilometre Stone (ordinary)1687687
7Transportation of GSB15010050100
8बोर्ड130003000
Total Material 135000