S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 1000 | 1000 |
2 | Setting out work Refferance pillers, refferancing bench mark and temporary bench mark Construction of Reference Bench Mark 50x50x70 cm. made of 1:3:6 cement concrete i/c excavation of 50x50x50 cm pit, working benchmark 30x30x45 cm at every 500 m interva | 1468.23 | 412.32 | 605380.5936 |
3 | Site clearance, cutting grass, raking into heaps and removing off the premises | 1125.2 | 59.6 | 67061.92 |
4 | Labour only for lime mortar & lime surkhi mortar | 623 | 55.69 | 34694.87 |
5 | Providing and laying in foundation, plinth and under floors lime concrete with 40mm nominal size graded stone aggregates (metal) and 40% lime mortar. i/c ramming in layers and curing complete excluding cost of form work.-Lime mortar 1:3 (1lime putty, 3sand) | 2111.1 | 117.3 | 247632.03 |
6 | False work for R.C.C. and P.C.C. work in plinth and foundation | 741.85 | 68.22 | 50609.007 |
7 | Centering and shuttering for arch roof including all lead and lift. (for low cost House) | 400 | 32.6 | 13040 |