S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 180 | 0.5 | 90 |
2 | Filling in plinth with sand under floors including watering, ramming, consolidating and dressing complete. | 22.49 | 537.3 | 12083.877 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal) | 20.84 | 3067.2 | 63920.448 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 27 | 129 | 3483 |
5 | Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide) | 41 | 6.2 | 254.2 |
6 | Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for | 17.85 | 34.4 | 614.04 |
7 | Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 30 Kms. and part there of upto 50 Kms. | 10.25 | 703.1 | 7206.775 |
8 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 1 | 12500 | 12500 |
9 | Field Technical Supervisior Charge-FTSC | 1 | 1250 | 1250 |