State: MADHYA PRADESH District: KHANDWA Block: PANDHANA Panchayat: HEERAPUR RAIYAT
Work Code: 1725007034/WC/22012034316030 (निर्मल नीर फारेस्ट आफिस के पास)
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2016-2017 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : No Perspective Plan : No
Proposal Date : 15/8/2016 Work start date : 18/1/2017
Present status : Non-existent Proposed Status : Farm Pond
Tech Sanction Details
Technical Sanction No. : 613hir Sanction Date : 23/12/2016
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
184000 151000 0 0 0 0 0 151000 0 335000
Financial Sanction Details
Financial\Administrative Sanction No: 9hir Financial\Administrative Sanction Date 25/12/2016
Fin. Sanc. Amt. (in Rs) NREGA:335000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
335000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Labour only for item no.040287.17393399.63
2Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:2:4 (1cement, 2sand, 4graded stone aggregate 20 mm nominal size)11.153908.643580.89
3False work for R.C.C. and P.C.C. work in plinth and foundation163.19167.527334.325
4Steel work in single section including in cutting, hoisting fixing in position in R.S. joists, channels, angles, tee.51.9461.43189.116
5Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Cold twisted / Hot rolled deformed / Thermo mechanicaly treated steel bars350.1666.423250.624
6Extra rates for quantities of work executed. In or under water or in foul condition (extra rate for the main item concerned is allowed on account of slow progress of works)118.11144.817102.328
7Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work288.4176.8
8Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed- Dense or hard soil for Tank Work31.79130.34142.237
9Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard moorum for Well Work488.4353.6
10Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard moorum for Tank Work63.59141.89017.062
11Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Disintegrated or soft rock (not requiring blasting) for Tank Work63.59406.8725872.8633
12Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard rock requiring blasting for Tank Work209.34669.98140253.6132
13work charge365.4810036548
Total Activity 335000
S.NoMaterialQuantityUnit PriceTotal
110 mm -  M.S. rod410.564016422.4
28 mm -  M.S. rod000
3Binding wire000
4Blasting Holas34115051150
5Centring & Shuttering10210021000
6CONTERGENCY125002500
7Gitti-20 mm418007200
8SIGNBOARD120002000
9Tools & Plant150005000
10रेत15100015000
11सिमेंट10030030000
Total Material 151000