S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 400 | 1.8 | 720 |
2 | Earth work in rough excavation,filling excavated earth into depressions on banking as directed ,top surface to be levelled and neatly dressed.-Dense or hard soil | 195 | 96.4 | 18798 |
3 | contingency | 1 | 700 | 700 |
4 | Labour difference in case of old SoR | 1 | 248 | 248 |