Govt. of India
Ministry of Rural Development
Department of Rural Development
The Mahatma Gandhi National Rural Employment Guarantee Act 28-Sep-2024 12:41:01 AM 
Back  
State: MADHYA PRADESH District: REWA Block: SIRMOUR Panchayat: JIWAR
Work Code: 1713003015/RC/22012034335618 (shudur rod nirman pathar kher se jiwar tak)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2016-2017 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 26/4/2016 Work start date : 2/2/2017
Present status : No Road Proposed Status : Construction of Gravel Road Roads for Community
Tech Sanction Details
Technical Sanction No. : 1784/1 Sanction Date : 27/1/2017
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
302000 548000 0 0 0 0 0 548000 0 850000
Financial Sanction Details
Financial\Administrative Sanction No: 46565.. Financial\Administrative Sanction Date 2/3/2017
Fin. Sanc. Amt. (in Rs) NREGA:850000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
850000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard115001500
2Site clearance, cutting grass, raking into heaps and removing off the premises80001.814400
3Dag-beling-Single spade stroke minimum 75mm deep0.33000900
4Collection of approved soil having CBR not less than 5, including stacking at quarry.1100000100000
5Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.1116000116000
6Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making1200000200000
7Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor1100000100000
8Compaction of hard shoulder collected at site, i/c making 4-5% camber by tractor mounted grader or labourers, watering at OMC and compacting with 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7)1100000100000
9Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP:1200000200000
10Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Loose or soft soil for Tank Work15933.75933.7
11Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.13074.83074.8
12Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Disintegrated or soft rock (not requiring blasting) for Tank Work17462.97462.9
Total Activity 850000
S.NoMaterialQuantityUnit PriceTotal
120 mm -  M.S. rod12500025000
22048-Construction of gravel ba15000050000
340 mm Metal12500025000
4BGSY SIGN BOARD130003000
5Cement10030030000
6collection and transportation 14000040000
7construcation of hard shoulder15000050000
8embankment with approved mater12500025000
9hume pipe np3-600mm13000030000
10Loosening Machine Rent14000040000
11roler17000070000
12Sand for filling and road blin12000020000
13Transportation Of Earth Work14000040000
14Transportation Of Material1100000100000
Total Material 548000