State: MADHYA PRADESH District: KHANDWA Block: CHHAIGAON MAKHAN Panchayat: SILODA
Work Code: 1725006045/RC/22012034164909 (पंच पर0 सी0 क्रा0 आंत पथ नाली निर्माण संपत के घर स)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2011-2012 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 1/3/2012 Work start date : 19/3/2012
Present status : Earthern road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 00584 Sanction Date : 1/3/2012
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Panchparmeshwar scheme2 scheme3 Total
54000 36000 0 0 163000 0 0 199000 0 253000
Financial Sanction Details
Financial\Administrative Sanction No: 002785 Financial\Administrative Sanction Date 19/3/2013
Fin. Sanc. Amt. (in Rs) NREGA:90000 Panchparmeshwar
163000
Scheme 2
0
Scheme 3
0
Total
253000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Dag-beling-Double spade "v" shaped stroke 100mm deep2940.4117.6
2Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)65.762608.7171548.112
3False work for R.C.C. and P.C.C. work in plinth and foundation211.8128.627237.48
4Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide)2935.81699.4
5Collection of approved soil having CBR not less then 12, including stacking at quarry.62.971187430.46
6Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 62.976377.82
7Transportation of metal 64.4833.52160.08
8Transportation of metal 129161.520833.5
9Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work9081.67344
10work charge13600113600
Total Activity 253000
S.NoMaterialQuantityUnit PriceTotal
120 MM B.T.METAL49766.437553.6
240 M.M. METAL100
3Cement350305106750
4Centring & Shuttering19087.5516634.5
5contengency223548940
6mason perday03500
7Mixer Machien202304600
8murrom5483.884529.52
9photocopy7811781
10sand cum25569.7614244
11Sand for filling and road blin100
12Thermocoal2010200
13Transportanion of WATER for Mu546324
14Transportation charges05000
15transpotation of matel5833.51943
16साईनबोर्ड 125002500
Total Material 199000