State: MADHYA PRADESH District: SATNA Block: UNCHAHARA Panchayat: BRHAREE
Work Code: 1712004016/WC/22012034426362 (नवीन तालाब निर्माण कार्य भर्री )
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2018-2019 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 15/8/2018 Work start date : 4/10/2018
Present status : Existing Proposed Status : Constr of Earthen Check Dam for Community
Tech Sanction Details
Technical Sanction No. : 432_2018-19 Sanction Date : 16/9/2018
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
1090000 280000 0 0 0 0 0 280000 0 1370000
Financial Sanction Details
Financial\Administrative Sanction No: 07-2018-19 Financial\Administrative Sanction Date 16/9/2018
Fin. Sanc. Amt. (in Rs) NREGA:1370000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
1370000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Site clearance, cutting grass, raking into heaps and removing off the premises3450310350
222cm thick dry stone pitching (without quarry spalls) with individual stone of 22cm depth and minimum size 0.014675260.4175770
3FOR EARTHEN DAM - Puddle filling of good clay including lead upto 50m including mixing watering and kneeding by tamping ramming and laying etc.612474.6290455.2
4FOR EARTHEN DAM - Construction of rock toe in earthen embankments including laying and hand packing, dressing, wedging and finishing over surface with.-Boulders3503.88172.46604279.1448
5Lossening of hard soil by ploughing the existing gound130552.768773.5
6Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed1167.96183.16213923.5536
7Field Technical Supervisior Charge-FTSC16448.6026448.602
Total Activity 1370000
S.NoMaterialQuantityUnit PriceTotal
1Display board130003000
2FTSC-Field Technical supervisi12600026000
3pitching stone lead 20 km6759362775
4Soil transport420040.5170100
5Transpotation of Puddle Earth61228.517442
Total Material 280000