S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 256 | 6.059921875 | 1551.34 |
2 | (a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 232.39 | 3778.59189293859 | 878106.97 |
3 | (c) C.C. 1:4:8 (1cement, 4sand, 8metal) | 15.04 | 2785.25997340426 | 41890.31 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation. | 383.28 | 161.65098622417 | 61957.59 |
5 | 22cm thick dry stone picked up boulder pitching i/c picking of boulder with individual size of 22cm depth. | 34.4 | 195.094476744186 | 6711.25 |
6 | (XV) 10 Km. Lead | 211.37 | 228.421062591664 | 48281.36 |
7 | (XVI) 12 Km. Lead | 7.57 | 343.828269484808 | 2602.78 |
8 | (XVIII) 16 Km. Lead | 52.93 | 251.938976006046 | 13335.13 |
9 | (XX) 20 Km. Lead | 106.84 | 282.845750655185 | 30219.24 |
10 | (b) Dense or hard soil | 2871.29 | 135.26752087041 | 388392.28 |
11 | Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works ) | 1 | 3530.01 | 3530.01 |