S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 150 | 6.64526666666667 | 996.79 |
2 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 22.86 | 3170.20909886264 | 72470.98 |
3 | (d) In Cement mortar 1:5 (1cement, 5sand) | 88.45 | 2969.80621820237 | 262679.36 |
4 | (e) In Cement mortar 1:6 (1cement, 6sand) | 104.4 | 2845.12653256705 | 297031.21 |
5 | Steel work welded in built up sections, framed work, including cutting hoisting fixing in position in gratings, frames, guard bars, ladders, railing, brackets and similar works & trusses and trussed purlins up to 25m span and 15 m over all height | 100 | 86.068 | 8606.8 |
6 | Collection of rubble masonry (size 0.014cum to 0.06cum) other then black trap, basalt or granite. | 192.85 | 645.248638838475 | 124436.2 |
7 | b (iii) Dense or hard soil for Tank Work | 4995 | 136.30625025025 | 680849.72 |
8 | (b) Dense or hard soil | 127.26 | 148.333254754047 | 18876.89 |
9 | Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works ) | 1 | 3613.85 | 3613.85 |