State: MADHYA PRADESH District: BHIND Block: ATER Panchayat: KACHPURA
Work Code: 1702001003/AV/22012034629422 (खेल मैदान रोहिन्दा)
Work Category: Anganvany
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2022-2023 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Perspective Plan :
Proposal Date : 3/10/2022 Work start date : 1/12/2022
Present status : NEW Proposed Status : Construction of Play field for Community
Tech Sanction Details
Technical Sanction No. : 1702001/2022-2023/14204/TS Sanction Date : 1/2/2023
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
SK/SemiSK Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
275638.68 137147.14 1323.83 2488.23 0 0 0 141000 0 416597.88
Financial Sanction Details
Financial\Administrative Sanction No: 1702001/2022-2023/14204/AS Financial\Administrative Sanction Date 10/2/2023
Fin. Sanc. Amt. (in Rs) NREGA:416594 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
417000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Single spade stroke minimum 75mm deep8090.404561186650185327.29
2(a) C.C. 1:2:4 (1cement, 2sand, 4metal)24196.4258392.85
3(c) C.C. 1:4:8 (1cement, 4sand, 8metal)1.1173036.472694717993391.74
4(k) Cement mortar 1:8 (1cement, 8sand)3.7044513.4611231101516717.86
5(b) In cement mortar 1:417.9630.72234636871511289.93
6(d) Cement mortar 1:6 (1cement, 6sand)43.6109.4172018348624770.59
7Compaction of soil for construction of subgrade & earthen shoulders with approved transported material collected and stacked at site, i/c spreading, making 4% camber and required gradient by tractor mounted grader or labourers, watering at OMC and compacted by 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7). Complete compaction work as per specifications for rural roads (MORD) clause 303, i/c required leads and lifts of materials etc. complete.2328.127.542618444224964121.97
8(b) Dense or hard soil5.591156.787694509032876.6
9Loosing of hard soIl such as moorum etc. By ploughing (tractor ect.) the existing ground exceeding 30cm in depth as well as 10 sqm on plan including all running expanses of machine.3611.8253.0510005329715611019.68
10Spreading dressing, breaking of clods of ploughed earth upto 20m lead and lift upto 1.5m disposed soil to be leveled and neatly dressed.3611.82579.0971738663972285685.15
Total Activity 407000
S.NoMaterialQuantityUnit PriceTotal
10002-Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper0.3969471000396.947
20038-Tractor with ripper attachment3.18949725208037.53244
30055-Smooth Wheeled Roller 8 to 10 tonne33.291833009987.549
40057-Water Tanker 5 to 6 KL Capacity46.5621205587.44
50297-Stone Aggregate(single size): 10 mm nominal size0.22650143
60367-Portland Cement1.272072864008141.26592
70982-Coarse sand (zone III)0.52499979.2514.070208
80983-Fine sand (zone IV)2.724285810252792.392945
91004-Average rate of mild steel round bars for reinforcements0.12536400801.92
103-Display Board / CIB11000010000
117900-Modular common burnt clay bricks of class designation 7.52910.585.215135.016
12MR6001-Stone Aggregate(single size): 40 mm nominal size other than BT1.76605500883.025
13MR6039-Water2793720.0616762.32
14MR6082-Stone Aggregate (Metal) 20mm nominal size (BT Metal) (Rate at quarry)0.70808790559.3832
15MR6089-Hire Charges for tractor with ploughing arrangement including running expanses and driver16.25321256009751.9275
Total Material 89500