S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 4.5 | 882 | 3969 |
2 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 3.75 | 3307.4 | 12402.75 |
3 | Random / uncoursed rubble masonry in plinth and foundation with mud mortar including levelling at plinth level. | 33.75 | 1858.1 | 62710.875 |
4 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Ruled pointing | 75 | 78.5 | 5887.5 |
5 | Transportation of metal | 7.68 | 419.7 | 3223.296 |
6 | Transportation of sand | 15.95 | 377.73 | 6024.7935 |
7 | Transportation rates for Masonry stone. | 33.75 | 384.58 | 12979.575 |
8 | Transportation rates for Boulders, Laterite, rubble pitching stones and excavated hard rock. | 1.48 | 123.09 | 182.1732 |
9 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 2.56 | 177.93 | 455.5008 |
10 | SIGN BOARD | 1 | 5000 | 5000 |
11 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 63.75 | 52.7 | 3359.625 |
12 | contingency | 1 | 1104.9115 | 1104.9115 |