Govt. of India
Ministry of Rural Development
Department of Rural Development
The Mahatma Gandhi National Rural Employment Guarantee Act 28-Sep-2024 12:19:53 AM 
Back  
State: MADHYA PRADESH District: DHAR Block: MANAWAR Panchayat: Rajukhedi
Work Code: 1722/WC/22012034430800 (Nistar Talab Galsingh ke Khet ke Pass)
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2018-2019 Execution Level : ZP
Execution Agency : Rural Engineering Services(04004) Work Status : Approve
Included in Annual Plan : No Perspective Plan : No
Proposal Date : 11/11/2018 Work start date : 4/1/2019
Present status : Non-existent Proposed Status : Constr of Earthen Check Dam for Community
Tech Sanction Details
Technical Sanction No. : 22/480 Sanction Date : 18/12/2018
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
2715000 1811000 0 0 0 0 0 1811000 0 4526000
Financial Sanction Details
Financial\Administrative Sanction No: 22/05 Financial\Administrative Sanction Date 2/1/2019
Fin. Sanc. Amt. (in Rs) NREGA:4526000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
4526000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Site clearance, cutting grass, raking into heaps and removing off the premises3851.25311553.75
2Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal)26.692562.568393.125
322cm thick dry stone pitching (without quarry spalls) with individual stone of 22cm depth and minimum size 0.0141686.23165278227.95
4Transportation of metal 5220.29172.4899977.996
5Transportation of metal 9777.49183.161790845.0684
6FOR EARTHEN DAM - Puddle filling of good clay including lead upto 50m including mixing watering and kneeding by tamping ramming and laying etc.1161.01474550318.74
7FOR EARTHEN DAM - Construction of rock toe in earthen embankments including laying and hand packing, dressing, wedging and finishing over surface with.-Boulders635.29574.6365037.634
8Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed2477.6752.7130573.209
9FTSC- Field supervision charges4310100431000
Total Activity 4526000
S.NoMaterialQuantityUnit PriceTotal
122 CM Piching Bolder Supplyes1686.2336.962221.887
2Boulder Transportation635.29293186139.97
3Contengency1550100155000
4Lead of Casing Soil 0.50 Km5220.2968.96359991.1984
5Lead of Casing Soil 4.00 Km9777.4973.26716298.9174
6Lead of Hearting Soil1161.01279.98325059.5798
7बोर्ड160006000
Total Material 1811000