S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 115 | 882 | 101430 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 60 | 3307 | 198420 |
3 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 56 | 3307 | 185192 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 85 | 148 | 12580 |
5 | Labour only for random/ uncoursed rubble masonry in any. Mortar for item no.0506 excluding labour for preparation of mortar. | 10 | 574 | 5740 |
6 | Coursed rubble masonry second sort in plinth and foundation.-In Lime mortar 1:2 (1lime putty, 2sand) | 400 | 2082 | 832800 |
7 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 882 | 127 | 112014 |
8 | Lossening of hard soil by ploughing the existing gound | 910 | 52 | 47320 |