S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 837.5 | 6.54194626865672 | 5478.88 |
2 | (a) Other then black trap Basalt or granite | 66.25 | 298.85841509434 | 19799.37 |
3 | (a) Consolidation of Moorum /earth work (rate for 1Cum. of Moorum /earth work) | 786.4 | 2.35124618514751 | 1849.02 |
4 | (XI) 6 Km. Lead | 66.25 | 261.068679245283 | 17295.8 |
5 | (XIV) 9 Km. Lead | 357.5 | 199.264111888112 | 71236.92 |
6 | (XXV) 30 Km. Lead | 275 | 366.695018181818 | 100841.13 |
7 | (III) 1.5 Km. Lead | 153.9 | 104.142949967511 | 16027.6 |
8 | (a) Boulders | 75 | 570.8252 | 42811.89 |
9 | For earthen dam - puddle filling of good clay including lead upto 20 meter including mixing, watering & kneading by tamping , ramming & laying etc. | 153.9 | 421.809096816114 | 64916.42 |
10 | Hearting, casing/cut off filling soil etc.
At optimum moisture content to achieve maximum dry density by mechanical sheep foot roller/ vibratory compacters including watering, required leads and lifts and material etc. complete. | 656.13 | 21.7463764802707 | 14268.45 |
11 | a (iii) Loose or soft soil for Tank Work | 43.88 | 99.3947128532361 | 4361.44 |
12 | b (iii) Dense or hard soil for Tank Work | 275 | 134.187490909091 | 36901.56 |
13 | c (iii) Hard moorum for Tank Work | 406.55 | 178.737769032099 | 72665.84 |
14 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 54.68 | 568.896122896854 | 31107.24 |