State: MADHYA PRADESH District: GWALIOR Block: BHITARWAR Panchayat: DEVRIKALA(P)
Work Code: 1703004033/RC/22012034328805 (C.C. Nirman Main Road se Laxman mirdha ke makan tak)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2015-2016 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : No Perspective Plan : No
Proposal Date : 26/1/2016 Work start date : 22/2/2017
Present status : Earthern road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 33/4653 Sanction Date : 8/2/2016
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Panchparmeshwar scheme2 scheme3 Total
41884 27988 0 0 193128 0 0 222000 0 263000
Financial Sanction Details
Financial\Administrative Sanction No: 33/035 Financial\Administrative Sanction Date 11/2/2016
Fin. Sanc. Amt. (in Rs) NREGA:69872 Panchparmeshwar
193128
Scheme 2
0
Scheme 3
0
Total
263000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Dag-beling-Single spade stroke minimum 75mm deep1800.354
2Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)60.33307.4199436.22
3False work for R.C.C. and P.C.C. work in plinth and foundation36147.85320.8
4Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 50 Kms. and part there of upto 100 Kms.51.26544.527911.07
5Unloading & stacking of cement from the-Railway wagon & stacking on Railway platform25.93184.234777.0839
6Loading of steel from the-Railway godown or store yard in to truck, dumper27131.493550.23
7Unloading of steel from the-Railway wagon & stacking on Railway platform13.27228.333029.9391
8Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing.2744.71206.9
9Collection of hard moorum including stacking at quarry.27142.53847.5
10Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 20metres and upto 1.5metre.-Dense or hard soil.351144914
11SIGN BOARD18891.548891.54
Total Activity 263000
S.NoMaterialQuantityUnit PriceTotal
120 MM B.T.METAL51.261444.574045.07
2Cement378278105084
3Centering and Shuttering3651.71861.2
4contangency and work charges117096.6317096.63
5SAND25.93784.2320335.0839
6Transportaion of muram (trip)2796.842614.68
Total Material 222000