State: MADHYA PRADESH District: GWALIOR Block: BHITARWAR Panchayat: DHOWAT(P)
Work Code: 1703004037/RS/22012034362016 (NALI NIRMAN SAITAN K MAKAN SE MAIN ROAD TAK)
Work Category: Rural Sanitation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2017-2018 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 14/4/2017 Work start date : 27/7/2017
Present status : Not Exist Proposed Status : Compost Pit
Tech Sanction Details
Technical Sanction No. : 37/215 Sanction Date : 23/7/2017
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
54017 68988 0 0 0 0 0 69000 0 123005
Financial Sanction Details
Financial\Administrative Sanction No: 37/015 Financial\Administrative Sanction Date 24/7/2017
Fin. Sanc. Amt. (in Rs) NREGA:123005 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
124000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Dag-beling-Single spade stroke minimum 75mm deep1100100
2Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering.8.248827267.68
3Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:6:12 (1 cement, 6sand, 12metal)6.183307.420439.732
4False work for R.C.C. and P.C.C. work in plinth and foundation12.2147.81803.16
5Coursed rubble masonry second sort in plinth and foundation.-In Cement mortar 1:8 (1cement, 8sand)27.452082.157153.645
6Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing55127.67018
7Lossening of hard soil by ploughing the existing gound65.8852.73471.876
8contingency12580025800
Total Activity 124000
S.NoMaterialQuantityUnit PriceTotal
1Cement7728021560
2transportation129002900
3Transpotation Charges11880018800
4गिटटी 3.541521.75386.818
5पत्‍थर90012.7511475
6रेत 49517.788801.1
Total Material 69000