State: MADHYA PRADESH District: KATNI Block: DHIMERKHEDA Panchayat: PADRBHATA
Work Code: 1744006059/RC/22012034292923 (खेत सड्क निर्माण भाग्यचन्द्र के खेत से राम प्रकाश कोल के खेत की ओर)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2015-2016 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 15/8/2015 Work start date : 15/12/2015
Present status : No Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 1760/059 Sanction Date : 3/12/2015
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
727000 622000 0 0 0 0 0 622000 0 1349000
Financial Sanction Details
Financial\Administrative Sanction No: 20/059 Financial\Administrative Sanction Date 4/12/2015
Fin. Sanc. Amt. (in Rs) NREGA:1349000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
1349000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Site clearance, cutting grass, raking into heaps and removing off the premises45001.56750
2Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.70003.725900
3Lime Surkhi Mortar 1:1:1 ( 1 lime putty, 1 surkhi, 1sand )586.8536.321302.655
4Contingency17000070000
5Work charge11200012000
6Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Loose or soft soil22.7999.62269.884
7Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead797.2323.618814.628
8Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)31.283231.5101081.32
9Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal)6.532451.816010.254
10False work for R.C.C. and P.C.C. work in plinth and foundation10.26132.31357.398
11Chain and compass survey.-Headworks/Other Works0.7792554.4
12Chain and compass survey.-Canals/Roads1628628
13Fly levelling for fixing temporary bench marks.-Upto 15 m interval0.7792554.4
14Levelling - Headwork.-Below 5 m interval0.715701099
15Levelling - Headwork.-5 to 10 m interval0.715701099
16Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.1740164.25285795
17Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing.4983.6944.1219780.729
18Providing laying and compacting of 40mm thick metal renual coat in wet season including picking old road surface, spreading of clean and crushed aggregate grading - 3, screenings and korebandi and rolling with power roller exceeding 8 tonne as per MOST 20326.03544.9177653.747
19Providing and laying reinforced cement concrete pipes N.P.3 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-900 mm dia.7.53125.623442
20Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making1594.421.634439.04
21Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to Table 2.2 of IRC:SP:77-2008, having Liquid Limit less than 25 and Plasticity inde270729.28196905.6
22Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP:108.68381.941504.892
23Collection of soft moorum including stacking at quarry.740121.389762
Total Activity 1349000
S.NoMaterialQuantityUnit PriceTotal
12043 soil Compaction material586.8536.321302.655
22045-compection of hard solder154023.736498
32049-Construction of gravel su90508.545765
4BGSY Information Board in Ceme150005000
5Compaction of Earth Work79723.618809.2
6contigency140004000
7hume pipe404000160000
8Kilometre Stone (200 M)53251625
9km stone25501100
10Transportation Of Selected Soi1740164.25285795
11Transportation of Water26015941340
Total Material 622000